• Wiley Project Director, Graham Harvey with the award.
    Wiley Project Director, Graham Harvey with the award.
Close×

The self-sustaining biogas facility at JBS Australia’s Dinmore facility has won its creator, Wiley, another award.

The meat company's biogas and water treatment plant, which was designed and constructed by Wiley, has taken out the award for Innovation in Environmental Management at the recent Queensland Master Builders Association (QMBA) State Awards.

It marks the second award Wiley has won for the project, after taking home the same category at QMBA’s regional awards earlier this year.

The biogas facility at JBS Australia’s Dinmore facility captures cattle emissions to power an existing natural gas-fired boiler plant, reducing annual greenhouse gas emissions by 89 per cent and saving more than $1 million a year on natural gas costs.

Wiley MD, Tom Wiley, said winning both the regional and state award for Innovation in Environmental Management is an exciting achievement for the company.

“Rather than shy away from complex projects, we actively seek them out to continually evolve our thinking, processes, and solutions.”

Wiley Project Director, Graham Harvey, said: “This is an industry benchmark demonstrating the reality of environmental processing solutions for heavy emission producers. It is a great win for Wiley, JBS Australia, and everyone involved.”

 The project’s key solutions included:

  • Construction of a new 20ML Covered Anaerobic Lagoon (CAL).
  • Covering of two existing Anaerobic Lagoons (AL) with high density polyethylene (HDPE) to capture biogas, and then burn the gas through the boiler to provide energy for the plant.
  • Installation of a biogas train to pipe biogas from the CALs to a central flare and then to the existing 10MW boiler.
  • Upgrade of Waste Water Treatment Plant (WWTP) with a new Dissolved Air Flotation (DAF) unit.

Packaging News

The merger between packaging giants Amcor and Berry is now complete, with the all-scrip deal creating a company with some 400 packaging plants, and 75,000 staff, located in 140 countries.

Pact Group is facing softening demand in Q4, citing Donald Trump’s tariffs, the ongoing domestic cost of living pressures, and supply chain disruption with shipping container supply tightening.

Raphael Geminder is following through on his stated intention to delist Pact Group in light of his failed takeover of the company, and has set 16 July as the date he wants it off the ASX.